So in the past three weekends, we've gotten more done than the contractor had in the previous month: Nearly all the trim is done by us(except where we are waiting for some cabinet-side "skins" from Thomasville to hide damage), we've had a plumber in to do all the sink, dishwasher, etc. work, we brought the folks who originally installed our fence back to repair it, and lots of painting and hole-filling. If you take a look at the flickr set, every wall was full of dings and bumps and we had to repaint the whole thing.
We built the doorway for the broom closet -- that came out very nicely.
What's left?
Rebuilding the vent hood soffit
About a day's work for the electrician (the vent hood, undercab lights, hooking up the power windows and a couple of fixtures)
Installing the screen door
Installing an automatic closer on the door to the garage
A LOT of yard work
A bit more painting of trim and such
Installing the bifold door for the broom closet
Fixing the siding where it was torn up at the start of the project
Some caulking around the stove, along the edges of the countertop and a couple of exterior spots
Final inspection
Probably only the first three items will be done by pros -- we can do the rest.
Oh, and the contractor stopped by to say he'll have the rest of the waivers to me next week. I'll believe it when I see it.